2 Hours
In only 2 hours the engineers gained valuable insight in their operations and improve their production process.
At this plant, demineralized water is produced. The water is demineralized using reverse osmosis, which involves using an external pressure to push the water through a semipermeable membrane against its chemical gradient. When this is done, the mineral contaminants are trapped and removed from the water. This process is intrinsically energy intensive and is best known for its application in desalination of seawater to produce fresh drinking water.
With the goal of reducing fines in mind, the team needed to pinpoint the cause of their high energy use. To do this, they used various TrendMiner functionalities to test their hypothesis and gain insight into the relationship between the flow rate and the power usage.
To begin their analysis, tags were created in TrendMiner to measure and display the total power consumption of the reverse osmosis unit and the total flow of treated water. Now, the engineers could proceed to analyze the relationship between these two variables.
With the flow and energy consumption tags on display, a two-month timeframe was selected. This timeframe was selected due to the number of fines received in that period. The tags were visualized independently of time via a scatterplot with the flow in the y-axis and power consumption in the x-axis. Following these steps, the team was presented with the graph.
Two different operation zones were very noticeable in the graph, and the team quickly came to two conclusions. Total energy consumption increased for the total amount of treated water, but the energy efficiency was different for producing with either one or two reverse osmosis skids. Power usage was much lower when operating with two reverse osmosis skids, especially at high production rates. With this information in hand, the team gained this valuable insight into their operations and the optimal number of reverse osmosis units for their process.
Through their work in TrendMiner, the team finally determined that there was a dependency between energy consumption and the number of pumps/skids running in parallel. As a result, they were able to achieve their goal of reducing their energy use. By optimising the number of reverse osmosis units for a given flow, the team will save energy, reduce fines, and save costs. This is especially impactful during winter months when energy usage limits were exceeded most often.
In only 2 hours the engineers gained valuable insight in their operations and improve their production process.
Through optimization of the production process the energy consumption could be kept below the maximum limit to avoid financial penalties.